The previous post looked at how South Korea has used data center waste heat so far. Europe has gone a step further and begun regulating it.
From 2027, the EU plans to issue every data center an energy efficiency label that also shows whether it is ready to supply its waste heat. Even if a data center does not supply heat today, the label will show whether it has the equipment to do so. This post covers how much waste heat European data centers reuse today and the EU rules on data center waste heat.
Waste heat reuse at European data centers today
The European Commission estimates that reusing an average of half of European data centers’ waste heat could cover the heating demand of almost 4 million European households. In practice, however, little of that heat is reused yet.
Since 2024, the EU has required data centers with at least 500kW of IT capacity to report their energy use, waste heat reuse and other figures every year. Of the 770 data centers in the first round of reporting in 2024, 67 reported reusing any waste heat at all, and about 1.8% of the heat produced by data centers was reused. The report notes, however, that some computed values seemed unrealistically high, so this figure may not fully represent waste heat reuse across the EU.
The EU report gives these reasons.
| Factor | Details |
|---|---|
| Readiness | Facilities differ in how well they are equipped to supply waste heat outside |
| Cost | Raising the heat’s temperature and delivering it to users takes investment |
| Timing | The heat on offer comes in an irregular pattern or not when it is needed |
| Demand | There is no one nearby to take the heat |
The report finds it difficult to set a target for the share of waste heat reused, because reuse is only possible where there is local demand for the heat and local infrastructure to deliver it. It notes that reuse usually does not pay off for small data centers, that in warmer regions data centers need cooling when homes and office buildings have very low to zero heating demand, and that even in regions with high heating demand, seasonal swings in demand remain a major difficulty.
EU rules on data center waste heat
The EU Energy Efficiency Directive (2023) requires data centers with a total rated energy input above 1MW to use their waste heat, unless they show that this is not technically or economically feasible. Germany set waste heat reuse shares for new data centers in its 2023 Energy Efficiency Act and is now discussing amendments to the law.
※ Energy Efficiency Directive: EU energy efficiency rules that member states must write into their national law
On 21 September 2026, the European Commission put forward a rating scheme for data centers. The scheme will enter into force after review by the European Parliament and the Council and publication in the Official Journal. From 2027, every data center that has reported to the EU database will then automatically receive an electronic label each year, showing its energy efficiency class and water use class along with whether it is waste heat reuse ready (yes/no). The labels will be publicly available in the EU database.
Here, waste heat reuse ready means having equipment such as heat exchangers, dedicated piping and heat meters so that the data center can supply waste heat outside its boundary. A data center counts as ready even without a heat pump to raise the heat’s temperature or an external heat network. Whether or not a data center reuses any waste heat today, it must report whether it is ready.
※ Data center label: like the energy efficiency rating on a fridge or air conditioner, a label that shows a data center’s energy efficiency class and other ratings
The EU is also considering minimum performance standards for data centers. It is collecting views until 14 December 2026, and the Commission has listed waste heat reuse among the example areas, together with energy efficiency and water use.
Where data center waste heat rules are heading
Of the four reasons for low waste heat reuse above, the one the EU label addresses directly is readiness, because the label shows whether a data center has the equipment to supply its waste heat.
One thing rules alone cannot easily solve is timing. When heat is produced at different times from when it is needed, having the equipment in place does not close that gap. Storing heat and drawing on it when needed can narrow it.
The bottom line
The EU requires data centers above 1MW to use their waste heat in principle, and from 2027 it plans to make public whether each data center has the equipment to supply its waste heat. Even data centers that do not yet supply heat will have their readiness shown, and minimum performance standards are also under consideration.
GIGAette’s IsoTES® is a constant-temperature thermal storage system that charges from whichever heat source fits — waste heat, renewable electricity or grid power — and releases the stored heat at a steady temperature.
If you would like to work out where the heat from your facility could be used, request a technical meeting.
Sources
- Report on the energy efficiency of data centres in the EU — European Commission, COM(2026) 500 (2026-09-21) — definition of PUE, 770 data centers in the first reporting round in 2024, 67 reporting waste heat reuse, about 1.8% of data center heat reused (with a footnote on representativeness), reasons for low reuse (readiness, investment, heat patterns, lack of offtakers), poor economics for small facilities, difficulty of setting ERF targets, seasonality, EU average PUE of 1.36
- Commission Delegated Regulation supplementing Directive (EU) 2023/1791 of the European Parliament and of the Council and amending Commission Delegated Regulation (EU) 2024/1364 as regards the establishment of a common Union rating scheme for data centres — European Commission, C(2026) 3472 (2026-09-21) — definition of waste heat reuse ready (heat exchangers, dedicated piping loop and heat meters, regardless of heat pumps or an external heat network), readiness reported regardless of reuse, label contents, annual labels from 2027, PUE classes A–G with boundaries (A 1.15 or less, G above 1.9), voluntary participation for data centers below 500kW or not yet in operation (design values for two years after start of operation, then actual values), labels publicly available in the EU database, energy for raising reused waste heat temperature subtracted from total energy (EDC), efficiency class based on PUE (calculated under Delegated Regulation (EU) 2024/1364, Annex III), heating demand of almost 4 million households if half of data center waste heat were reused
- Commission enhances energy efficiency and sustainability of data centres in the EU — European Commission press release, IP/26/1667 (2026-09-21) — rating scheme proposed, consultation on minimum performance standards opened, rating scheme subject to two-month scrutiny by Parliament and Council before entry into force, first labels expected in 2027, consultation closing on 14 December 2026
- Questions and answers on the Data centre energy efficiency package — European Commission (2026-09-21) — package contents (report, rating scheme, consultation on minimum performance standards), example areas for minimum performance standards (energy efficiency, water use, waste heat reuse)
- Directive (EU) 2023/1791 on energy efficiency — European Parliament and Council (2023-09-13) — Article 12 on data center reporting, Article 26(6) on waste heat use by data centers with a total rated energy input above 1MW (exempt if shown not technically or economically feasible)
- § 11 EnEfG (Energieeffizienzgesetz, Energy Efficiency Act) — German Federal Ministry of Justice, laws online (2023-11-13, in German) — data centers starting operation from 1 July 2026 must reach a share of reused energy of at least 10%, those starting from 1 July 2027 a planned share of at least 15%, and those starting from 1 July 2028 a planned share of at least 20% (to be met within two years of starting operation, with exemptions)
- Beschleunigte Umsetzung der Energieeffizienzrichtlinie beraten — German Bundestag (2026-09-24, in German) — first reading of the bill amending the Energy Efficiency Act (Drucksache 21/8027), committee hearing on 5 October 2026